Progress

Last update:11 Feb, 2016

Project progress

This project started its development in June 2014, and its expected completion date September 2017. Here we present the actions that comprise the project and its percentage of development. Each of these actions has a specific start and end date.

Implementation actions

0%

Global

Collection and treatment of the residue: 100%
Design and construction of the storage module: 100%
Pilot plant technical design: 100%
Pilot plant procurement and construction: 35%
Pilot plant demonstration: 0%
Viability study of energy/environmental/economic: 0%

Monitoring actions

0%

Global

Efectiveness of the project: 25%
Project socioeconomical impact: 20%

Communication and dissemination actions

0%

Global

Communication and dissemination of project results: 70%

Project management

0%

Global

Project management: 50%
Networking activities: 20%
After LIFE communication plan: 0%