Inglés Version en English

Progreso

Última actualización:21 Nov, 2016

Project progress

This project started its development in June 2014, and its expected completion date September 2017. Here we present the actions that comprise the project and its percentage of development. Each of these actions has a specific start and end date.

Implementation actions

0%

Global

Collection and treatment of the residue: 100%
Design and construction of the storage module: 100%
Pilot plant technical design: 100%
Pilot plant procurement and construction: 35%
Pilot plant demonstration: 0%
Viability study of energy/environmental/economic: 0%

Monitoring actions

0%

Global

Efectiveness of the project: 25%
Project socioeconomical impact: 20%

Communication and dissemination actions

0%

Global

Communication and dissemination of project results: 70%

Project management

0%

Global

Project management: 50%
Networking activities: 20%
After LIFE communication plan: 0%

La página web del proyecto WALEVA ya está en internet

The internet is an unrivalled source of information and has become a very important channel for communication. At the click of a mouse, a gigantic library of information is available to a wide number of people at any time. A well designed project website can be a key management tool, capable of improve the dissemination […]

Leer Más
storage_module_5

Diseño y construcción del módulo del almacenamiento

       

Leer Más
empacado 2

Recogia de paja de arroz

Leer Más
P1100153

Comienzo de etapa de molienda

Leer Más
life-waleva-project-2nd-visit-external-monitoring

Reunión de seguimiento mes 24

Leer Más
waleva-set-up-waleva-pilot-plant-advance_0000_00-portada

Montaje de la planta piloto WALEVA (grado de avance)

Leer Más